Tesseract Arena

Site progress — 17 August 2026

INTERNAL DISTRIBUTION
//  Status

Foundations are going in. The steel is built.

Foundation work is running across the arena footprint and the CRS wall is up along the site edge. The steel frame has been fabricated and primed at the works. We start erecting once one signature comes through.

24
Foundation pads set out
CRS
Retaining wall built
PEB
Steel fabricated and primed
1
Approval left before erection
//  Approved layout

Arena Permission Plan v6.1

Arena 40.38 × 62.8 m with a 15 × 15 m courtyard, office block 48 × 61.5 m, 6.1 m internal roads, on a 16,032 sq yd plot. Ridge height 11.9 m. Click to open the full drawing.

//  Aerial video

Drone passes over the site

Twenty clips flown on site. Click any frame to play.

//  Aerial stills

The site from above

Click any image for full resolution.

//  Site works

CRS retaining wall

Built along the site edge, holding the level for the arena platform and the access road beside it.

CRS wall and site accessWall in place along the boundary, plant and material working off the platform above.
//  Substructure

Foundations on the ground

Pads dug, blinded and reinforced across the grid, moving to pour.

//  Superstructure

Steel is fabricated and waiting

Primary members cut, welded, surface-treated and primed at the works, staged for dispatch. Nothing about the steel is holding this up.

//  What's holding erection

One approval chain, and we are at the first link

Each step unlocks the next. Our paperwork is done and lodged at every stage; what we are waiting on is the MRO signature to start the chain.

STEP 01 — OPEN
Revenue sketch
Lodged with F-Line and tax records. Waiting on the MRO to sign.
STEP 02
Architect certification
GHMC-empanelled architect certifies the drawing. Drawing complete at v6.1.
STEP 03
Build Now filing
Application goes into the Telangana Build Now portal once certified.
STEP 04
Erection
Steel comes off the works and goes up on the finished foundations.

Everything within our control is done. We are pushing daily for the MRO signature and will confirm the erection programme the day it lands.