// Status
Foundations are going in. The steel is built.
Foundation work is running across the arena footprint and the CRS wall is up along the site edge. The steel frame has been fabricated and primed at the works. We start erecting once one signature comes through.
24
Foundation pads set out
PEB
Steel fabricated and primed
1
Approval left before erection
// Approved layout
Arena Permission Plan v6.1
Arena 40.38 × 62.8 m with a 15 × 15 m courtyard, office block 48 × 61.5 m, 6.1 m internal roads, on a 16,032 sq yd plot. Ridge height 11.9 m. Click to open the full drawing.
// Aerial video
Drone passes over the site
Twenty clips flown on site. Click any frame to play.
// Aerial stills
The site from above
Click any image for full resolution.
// Substructure
Foundations on the ground
Pads dug, blinded and reinforced across the grid, moving to pour.
// Superstructure
Steel is fabricated and waiting
Primary members cut, welded, surface-treated and primed at the works, staged for dispatch. Nothing about the steel is holding this up.
// What's holding erection
One approval chain, and we are at the first link
Each step unlocks the next. Our paperwork is done and lodged at every stage; what we are waiting on is the MRO signature to start the chain.
STEP 01 — OPEN
Revenue sketch
Lodged with F-Line and tax records. Waiting on the MRO to sign.
STEP 02
Architect certification
GHMC-empanelled architect certifies the drawing. Drawing complete at v6.1.
STEP 03
Build Now filing
Application goes into the Telangana Build Now portal once certified.
STEP 04
Erection
Steel comes off the works and goes up on the finished foundations.
Everything within our control is done. We are pushing daily for the MRO signature and will confirm the erection programme the day it lands.
// Annexure
Documentation lodged
Click any document to open the original.
// Summary
Where we are
01 Site is established. Cleared, levelled, CRS wall up, plant and material on site.
02 Foundations are going in. Grid set out, dug, blinded and reinforced across the footprint.
03 Steel is built. Primary members fabricated, primed and staged at the works.
04 Approvals are sequenced. Revenue sketch lodged; certification and Build Now filing follow straight after.
05 Next milestone is erection. Programme confirmed the day the MRO signature is received.
Tesseract Arena · TGPA Junction, Kismatpur · 17 August 2026
Internal distribution